Rennes Metro

Line B (work package 3) with a north covered trench and associated station built inside a berliner wall

  • Civil engineering works

    • Covered trenches and shafts
metro-de-rennes-etpo-nantes-travaux-publics-ouvrages-d-art-et-genie-civil-1
metro-de-rennes-etpo-nantes-travaux-publics-ouvrages-d-art-et-genie-civil-2 metro-de-rennes-etpo-nantes-travaux-publics-ouvrages-d-art-et-genie-civil-3 metro-de-rennes-etpo-nantes-travaux-publics-ouvrages-d-art-et-genie-civil-4 metro-de-rennes-etpo-nantes-travaux-publics-ouvrages-d-art-et-genie-civil-5

Start of works

2014

Project owner

SEMTCAR

Contract

  • Transportation
  • Railway

Prime contractor

EGIS RAIL - EGIS BAT. CENTRE OUEST - ARCADIS ESG - L'HEUDE & L'HEUDE

Total of works Excl. TVA

33 128 000

Construction location

RENNES / FRANCE

Offers & solutions

  • Execution of port structures

Worksite figures

  1. Length: 1.2 km
  2. Width: 6 m
  3. Duration of the worksite: 33 months